Evaluation of delays in technical approval of UK Highways Act section 278 projects
Article
Bagheri, M. and Bate, E. 2024. Evaluation of delays in technical approval of UK Highways Act section 278 projects. Journal of Strategic Contracting and Negotiation. In Press. https://doi.org/10.1177/20555636241246192
Authors | Bagheri, M. and Bate, E. |
---|---|
Abstract | This paper attempts to address the causes of delays to the legal and technical approval processes involved in the creation of agreements authorising works to public highways under s.278 Highways Act (1980) specific to Warwickshire County Council, UK, and whether the type of contract (JCT or NEC) or s.278 agreement (minor or major) has any tangible influence. A series of questionnaires and interviews were carried out on a sample group of individuals including designers, developers, construction lawyers, and council engineers with extensive industry experience in relation to s.278 legal, technical, construction and adoption processes. The results revealed the key causes of delays, and therefore the barriers to prompt and efficient approval processes, as the lack of communication between developer and local authority, inexperienced developers’ engineers, poor quality drawings, and insufficient information in the local authority’s design guide. These key factors are discussed and recommendations are provided to tackle these issues. |
Keywords | s.278 agreement; Joint Contracts Tribunal; New Engineering Contract |
Journal | Journal of Strategic Contracting and Negotiation |
Journal citation | In Press |
ISSN | 2055-5636 |
2055-5644 | |
Year | 2024 |
Publisher | SAGE Publications |
Accepted author manuscript | License File Access Level Anyone |
Digital Object Identifier (DOI) | https://doi.org/10.1177/20555636241246192 |
Publication dates | |
Online | 20 May 2024 |
Publication process dates | |
Accepted | 01 Mar 2024 |
Deposited | 06 Mar 2024 |
Copyright holder | © 2024, The Authors |
Copyright information | Users who receive access to an article through a repository are reminded that the article is protected by copyright and reuse is restricted to non-commercial and no derivative uses. Users may also download and save a local copy of an article accessed in an institutional repository for the user's personal reference. For permission to reuse an article, please follow Sage's Process for Requesting Permission |
Additional information | This article version is the author's accepted manuscript, which has been published by SAGE Publications in the Journal of Strategic Contracting and Negotiation: https://journals.sagepub.com/doi/10.1177/20555636241246192 |
https://repository.uel.ac.uk/item/8x614
Download files
Accepted author manuscript
JSCAN-23-0011.R2_Proof_hi_FINAL.pdf | ||
License: CC BY-NC-ND 4.0 | ||
File access level: Anyone |
76
total views51
total downloads10
views this month10
downloads this month